The 220kV substation of Tangshan Ruifeng iron and Steel Co., Ltd. was successfully started and operated at one time

The 220kV substation of Tangshan Ruifeng iron and Steel Co., Ltd. was successfully started and operated at one time

  • Categories:Trade News
  • Author:
  • Time of issue:2021-06-03 11:11
  • Views:0

(Summary description)

The 220kV substation of Tangshan Ruifeng iron and Steel Co., Ltd. was successfully started and operated at one time

(Summary description)

  • Categories:Trade News
  • Author:
  • Time of issue:2021-06-03 11:11
  • Views:0
Information

Ruigang 220kV substation with 39 35kV voltage level outgoing line intervals supported by our company officially started operation with the issuance of the start order of State Grid Jibei electric power company. It experienced 125 operation steps including 220kV bus split phase impact and nuclear phase, main transformer impact and nuclear phase, 110KV, 35kV bus and distribution equipment impact and nuclear phase. The power transmission was successful at one time.

Scan the QR code to read on your phone

Copyright©Qinhuangdao LongDing Electric Co.,LTD. All Rights Reserved  Powered by 300.cn   冀ICP备10014981号-1

Add:No.110 West QinhuangRoad Deveilopment Zone.Qinhuangdao.Hebei  Tel:0335-8501711/0335-8501712  Fax:0335-8501713   Email

Qinhuangdao LongDing Electric Co.,LTD.
weibo
weix